Construction Updates
Construction began July 2025 and is estimated to be complete in late summer of 2026.
Construction Contacts:
Trip LeCorgne, Project Manager (504) 258-5332, tlecorgne@deneuveconstruction.com
Ben Hermsen, Superintendent (720) 560-8638 bhermsen@deneuveconstruction.com
Developer Contacts:
Gabby Carazo, Project Manager gabby@bluelinedevelopment.com
Amanda Ropek, Project Manager ARopek@BroomfieldHousingAlliance.org
Construction Progress
July 2025
The cul-de-sac is gone and the team is leveling the ground and preparing the site for utility work.
September 2025
Significant excavation has been completed to prepare the site for utility installation and the placement of foundational piers.
Cottonwood
Cottonwood